New Headers for Leases

Tuesday April 28th, 2015

We have built and installed two new headers (one for the Ferne lease and one for the Jerry Lee) and AWTs (automatic well testers) for each header. Existing wells are getting tied into the new header system which will eventually feed the new facility. We are also drilling 17 wells, most of which are on the Ferne and Jerry Lee leases. The steam generators- Two 85 million BTU dual pass generators capable of putting out 5700 BBls/day of 70% quality steam each, 11,400 total. In order to feed these two new generators we have built another soft water tank and increased our water processing capabilities.